Client report
HOA progress update
Period: Week of July 14–20
Prepared for: Riverside HOA
Date: July 20, 2026
Executive Summary
Tear-off is complete on buildings A–C. Underlayment is installed on A–B, with building C staged to continue Monday. One materials delay affects valley flashing at unit 12; alternate edge metal still needs owner sign-off. Remaining work is tracked on a short punch list with no reported water intrusion in completed areas.
Work Completed
- Tear-off completed on buildings A, B, and C
- Underlayment installed on buildings A and B
Photo 1 · Photo 2