HOA progress update
Multi-building re-roof status for property managers
Riverside HOA – Roof Renovation Phase 2 Progress Report
Period: Week of July 14–20
Prepared for: Riverside HOA
Date: July 20, 2026
Executive Summary
Tear-off is complete on buildings A–C. Underlayment is installed on A–B, with building C staged to continue Monday. One materials delay affects valley flashing at unit 12; alternate edge metal still needs owner sign-off. Remaining work is tracked on a short punch list with no reported water intrusion in completed areas.
Work Completed
- Tear-off completed on buildings A, B, and C
- Underlayment installed on buildings A and B
- Building C prepared and staged for underlayment
- Punch-list tracking updated (six open items)
Current Status
- Buildings A–B: ready for shingle install on south elevation of A
- Building C: underlayment next
- Valley flashing at unit 12: awaiting material (ETA Thursday)
- Weather: one rain day this period; no water intrusion reported in completed zones
Upcoming Work / Next Steps
- Complete underlayment on building C
- Begin shingle installation on building A south elevation
- Install valley flashing at unit 12 once material arrives
- Close remaining punch-list items (ridge vents, step-flashings)
Blockers or Risks
- Flashing material lead time for unit 12 valleys (ETA Thursday)
- Owner decision pending on alternate edge metal package at window-adjacent conditions
Recommendations
- Approve or reject the alternate edge metal package this week to avoid idle time after flashing arrives.
- Keep unit 12 valleys weather-protected until permanent flashing is installed.
- Review the six-item punch list at the next site walk so closeout stays on schedule.